Fort St. John, Peace River Site C Dam Clean Energy Project

Field Engineer at BC Hydro

Keywords

  • Field engineer (RET – Resident Engineering Team)
  • Concrete outline drawings
  • Concrete reinforcement drawings
  • Concrete pre-pour checklist
  • Rebar inspections
  • Quality Assurance
  • Update 3-D models

Details

Field Engineer

Read concrete outline and reinforcement drawings, Perform on-site rebar inspections and concrete pre-pour checks

  • Prepared concrete pour and rebar detail drawings and related documents and performed inspections individually
  • Provided solutions to onsite deficiencies collaboratively with team members, designers and other stakeholders

Update Project Status

Prepare, and update 3-D Models

  • Update 3-D models in five different working areas using Navisworks weekly to display upcoming work plans visually

Presentation

APSC 310 – Technical presentation assignment

According to UBC third coop work term assignment requirement, one technical presentation needs to be hosted by the end of the work term.

Presentation slides